28. Contract no. sWB/CT/10/2016 The delivery and Laying of 300mm dia d.I./355mm o.d.
hdPE Mains, Valves and Fittings cum ancillary Works along Jalan Kemuyang By-Pass off
Jalan Tunku abdul rahman, sibu
Contract Sum : RM174,438.90
Contract Period : 17.08.2016
Date of Practical Completion : 16.01.2017
Contractor : HK Engineering
Physical Work Done up to 31.12.2016 : 65%
Scheduled Progress up to 31.12.2016 : 65%
29. Contract no. sWB/CT/11/2016 The delivery and Laying of 160mm o.d. hdPE/63mm o.d.
P.a. Timur Mains, Valves, Fittings cum ancillary Works and Patching of Concrete asphalt at
Jalan Lebaan and Jalan Lanang (renewal)
Contract Sum : RM292,722.00
Contract Period : 17.08.2016
Date of Practical Completion : 05.11.2016
Contractor : Tuai Rumah Sijah
Enterprise
Expiry of Date of Defects Liability Period : 04.11.2017
30. Contract no. sWB/CT/14/2016 The supply and delivery of Fittings to sibu Water Board, sibu
for Proposed renewal of Main Projects
Contract Sum : RM70,680.00
Contract Period : 07.11.2016
Date of Practical Completion : 07.12.2016
Contractor : Mainline Enterprise
Sdn. Bhd.
Expiry of Date of Defects Liability Period : 06.06.2018
18 Sibu Water board
hdPE Mains, Valves and Fittings cum ancillary Works along Jalan Kemuyang By-Pass off
Jalan Tunku abdul rahman, sibu
Contract Sum : RM174,438.90
Contract Period : 17.08.2016
Date of Practical Completion : 16.01.2017
Contractor : HK Engineering
Physical Work Done up to 31.12.2016 : 65%
Scheduled Progress up to 31.12.2016 : 65%
29. Contract no. sWB/CT/11/2016 The delivery and Laying of 160mm o.d. hdPE/63mm o.d.
P.a. Timur Mains, Valves, Fittings cum ancillary Works and Patching of Concrete asphalt at
Jalan Lebaan and Jalan Lanang (renewal)
Contract Sum : RM292,722.00
Contract Period : 17.08.2016
Date of Practical Completion : 05.11.2016
Contractor : Tuai Rumah Sijah
Enterprise
Expiry of Date of Defects Liability Period : 04.11.2017
30. Contract no. sWB/CT/14/2016 The supply and delivery of Fittings to sibu Water Board, sibu
for Proposed renewal of Main Projects
Contract Sum : RM70,680.00
Contract Period : 07.11.2016
Date of Practical Completion : 07.12.2016
Contractor : Mainline Enterprise
Sdn. Bhd.
Expiry of Date of Defects Liability Period : 06.06.2018