14 Contract No. SWB/CT/26/2013 Tanjung Manis Water Supply Phase 1 Package 5 –
Proposed Construction of Twin 1100mm ND MSPUL Raw Water Submarine
Pumping Main Crossing Major Rivers (7 nos.)
Contract Sum : RM81,500,000.00
Date of Commencement : 11.11.2013
Date of Practical Completion : 10.11.2015
Contractor : PPES Works (Sarawak) Sdn. Bhd.
Consultant : Jurutera Perunding Wahba Sdn. Bhd.
Physical Work Done up to 31.12.2014 : 40.68%
Scheduled progress up to 31.12.2014 : 42.21%
15 Contract No. SWB/CT/27/2013 Tanjung Manis Water Supply Phase 1 Package 6 –
Proposed Water Treatment and Associated Facilities and High Level Tank at Tanjung Manis
Contract Sum : RM105,350,000.00
Date of Commencement : 11.11.2013
Date of Practical Completion : 10.11.2015
Contractor : Naim Engineering Sdn. Bhd.
Consultant : Jurutera Perunding Wahba Sdn. Bhd.
Physical Work Done up to 31.12.2014 : 59.02%
Scheduled progress up to 31.12.2014 : 45.61%
16 Contract No. SWB/CT/28/2013 Tanjung Manis Water Supply Phase 1 Package 7 – Proposed Raw
Water Storage Reservoir and Intake and Booster Pumping Station at Tanjung Manis
Contract Sum : RM71,700,000.00
Date of Commencement : 11.11.2013
Date of Practical Completion : 10.11.2015
Contractor : JV Utraco Construction Sdn. Bhd./
Pembinaan Kuantiti Sdn. Bhd.
Consultant : Jurutera Perunding Wahba Sdn. Bhd.
Physical Work Done up to 31.12.2014 : 54.10%
Scheduled progress up to 31.12.2014 : 55.22%
17 Contract No. SWB/CT/29/2013 Tanjung Manis Water Supply Phase 1 Package 8 –
Proposed Distribution Pipelines at Tanjung Manis
Contract Sum : RM61,000,000.00
Date of Commencement : 11.11.2013
Date of Practical Completion : 10.11.2015
Contractor : Quality Concrete Holdings Berhad
Consultant : Jurutera Perunding Wahba Sdn. Bhd.
Physical Work Done up to 31.12.2014 : 52.79%
Scheduled progress up to 31.12.2014 : 32.82%
18 Contract No. SWB/CT/02/2014 Projek Pemasangan Paip Utama untuk Zon 60
Di Jalan Tun Ahmad Zaidi Adruce (Stage 2), Sibu, Sarawak
Contract Sum : RM3,867,700.00
Date of Commencement : 11.3.2014
Date of Practical Completion : 10.6.2015
Contractor : Mainline Enterprise Sdn. Bhd.
Consultant : Jurutera Perunding Wahba Sdn. Bhd.
12 Physical Work Done up to 31.12.2014 : 73.90%
Scheduled progress up to 31.12.2014 : 69.90%
Proposed Construction of Twin 1100mm ND MSPUL Raw Water Submarine
Pumping Main Crossing Major Rivers (7 nos.)
Contract Sum : RM81,500,000.00
Date of Commencement : 11.11.2013
Date of Practical Completion : 10.11.2015
Contractor : PPES Works (Sarawak) Sdn. Bhd.
Consultant : Jurutera Perunding Wahba Sdn. Bhd.
Physical Work Done up to 31.12.2014 : 40.68%
Scheduled progress up to 31.12.2014 : 42.21%
15 Contract No. SWB/CT/27/2013 Tanjung Manis Water Supply Phase 1 Package 6 –
Proposed Water Treatment and Associated Facilities and High Level Tank at Tanjung Manis
Contract Sum : RM105,350,000.00
Date of Commencement : 11.11.2013
Date of Practical Completion : 10.11.2015
Contractor : Naim Engineering Sdn. Bhd.
Consultant : Jurutera Perunding Wahba Sdn. Bhd.
Physical Work Done up to 31.12.2014 : 59.02%
Scheduled progress up to 31.12.2014 : 45.61%
16 Contract No. SWB/CT/28/2013 Tanjung Manis Water Supply Phase 1 Package 7 – Proposed Raw
Water Storage Reservoir and Intake and Booster Pumping Station at Tanjung Manis
Contract Sum : RM71,700,000.00
Date of Commencement : 11.11.2013
Date of Practical Completion : 10.11.2015
Contractor : JV Utraco Construction Sdn. Bhd./
Pembinaan Kuantiti Sdn. Bhd.
Consultant : Jurutera Perunding Wahba Sdn. Bhd.
Physical Work Done up to 31.12.2014 : 54.10%
Scheduled progress up to 31.12.2014 : 55.22%
17 Contract No. SWB/CT/29/2013 Tanjung Manis Water Supply Phase 1 Package 8 –
Proposed Distribution Pipelines at Tanjung Manis
Contract Sum : RM61,000,000.00
Date of Commencement : 11.11.2013
Date of Practical Completion : 10.11.2015
Contractor : Quality Concrete Holdings Berhad
Consultant : Jurutera Perunding Wahba Sdn. Bhd.
Physical Work Done up to 31.12.2014 : 52.79%
Scheduled progress up to 31.12.2014 : 32.82%
18 Contract No. SWB/CT/02/2014 Projek Pemasangan Paip Utama untuk Zon 60
Di Jalan Tun Ahmad Zaidi Adruce (Stage 2), Sibu, Sarawak
Contract Sum : RM3,867,700.00
Date of Commencement : 11.3.2014
Date of Practical Completion : 10.6.2015
Contractor : Mainline Enterprise Sdn. Bhd.
Consultant : Jurutera Perunding Wahba Sdn. Bhd.
12 Physical Work Done up to 31.12.2014 : 73.90%
Scheduled progress up to 31.12.2014 : 69.90%