9 Contract No. SWB/CT/11/2013 Design, Supply, Install and Commissioning of One (1) Unit of
VODES 6500 (Electrochlorination) On-Site Chlorine Generation System for Sibu Water Board

Contract Sum : RM812,100.00
Date of Commencement : 07.08.2013
Date of Practical Completion : 27.12.2013
Contractor : Solidium (Sarawak) Sdn. Bhd.
Expiry Date of Defects Liability Period : 26.12.2014


10 Contract No. SWB/CT/21/2013 The Supply, Delivery, Installation, Testing and Commissioning of
Six (6) Units of Electric Valve Actuator c/w Value Accessories for Existing 750mm Filter Outlet
Butterly Valve at Salim Water Treatment Plant Phase 1, Sibu Water Board, Sibu

Contract Sum : RM126,300.00
Date of Commencement : 01.10.2013
Date of Practical Completion : 28.03.2014
Contractor : Chun Hua Sdn. Bhd.
Expiry Date of Defects Liability Period : 27.03.2015

11 Contract No. SWB/CT/23/2013 Tanjung Manis Water Supply Phase 1 Package 1 – Proposed Raw
Water Intake Using River Bank Filtration System (RBF)

Contract Sum : RM73,987,000.00
Date of Commencement : 11.11.2013
Date of Practical Completion : 10.11.2015
Contractor : KCK Konsortium Sdn. Bhd.
Consultant : G&P Professional (Sarawak) Sdn. Bhd.
Physical Work Done up to 31.12.2014 : 15.59%
Scheduled progress up to 31.12.2014 : 35.24%
12 Contract No. SWB/CT/24/2013 Tanjung Manis Water Supply Phase 1 Package 3 – Proposed
Jointing, Laying, Testing and Commissioning of the 1600 ND MPSUL Raw Water Pumping Main

Contract Sum : RM109,250,000.00
Date of Commencement : 11.11.2013
Date of Practical Completion : 10.11.2015
Contractor : Microsite Enterprise Sdn. Bhd.
Consultant : Jurutera Perunding Wahba Sdn. Bhd.
Physical Work Done up to 31.12.2014 : 51.50%
Scheduled progress up to 31.12.2014 : 59.10%

13 Contract No. SWB/CT/25/2013 Tanjung Manis Water Supply Phase 1 Package 4 – Proposed
Raw Water Booster Pumping Station at Sg. Maaw Raw Water Intake Site

Contract Sum : RM86,700,000.00
Date of Commencement : 11.11.2013
Date of Practical Completion : 10.11.2015
Contractor : Hock Seng Lee Berhad
Consultant : Jurutera Perunding Wahba Sdn. Bhd.
Physical Work Done up to 31.12.2014 : 25.26%
Scheduled progress up to 31.12.2014 : 36.01%