CorPoraTE ProgrEss



dEVELoPMEnT
PLans
The major development of the Board under the 10 Malaysia Plan included implementation of the following
th
projects:
1. Program Mengurangkan Kadar Air Tak Berhasil Negeri Sarawak – Lembaga Air Sibu
2. Projek Pemasangan Paip Utama Zon 60 Di Jalan Tun Ahmad Zaidi Adruce, Sibu Division, Sarawak
3. Tanjung Manis Water Supply Phase 1
4. Membaikpulih Sistem Agihan Negeri Sarawak – Lembaga Air Sibu


dEVELoPMEnT ProgrEss
The Board had allocated RM15.13 for development projects in 2014, which marked the four (4) year of
the 10th Malaysia Plan. Total amount spent was RM12.76 which was made up of NRW Programme
RM3.54 million or 27.74%, Projek Pemasangan Paip Utama di Jalan Tun Ahmad Zaidi Adruce RM2.92
or 22.89%, Membaikpulih Sistem Agihan Negeri Sarawak RM5.51 million or 43.18% and other
development RM0.79 or 6.19%.

For Tanjung Manis Water Supply Phase 1, the Board is implementing the project on behalf of the State
Government. The fund is allocated to the Board as grant based on submission of claims from consultants,
contractors and other Agencies.


1 Contract No. SWB/CT/20/2011 The Delivery and Laying of D.I./HDPE Mains,
Valves and Fittings Cum Ancillary Works (Renewal Project Year 2011 – Package 1, 2 & 3)


Contract Sum : RM3,094,400.00
Date of Commencement : 01.12.2011
Date of Practical Completion : 13.05.2013
Contractor : Mainline Enterprise Sdn. Bhd.
Expiry Date of Defects Liability Period : 12.05.2014

2 Contract No. SWB/CT/24/2011 The Supply, Delivery and Commissioning of i2O
Pressure Management System and the Associated Accessories for Sibu Water Board.

Contract Sum : RM249,250.00
Date of Commencement : 17.01.2012
Date of Practical Completion : 25.05.2012
Contractor : ExxorTechnologies Sdn. Bhd.
Expiry Date of Warranty Period : 24.05.2014

3. Contract No. SWB/CT/03/2012 Projek Pemasangan Paip Utama Di
Jalan Tun Ahmad Zaidi Adruce (Zone 60m), Sibu Division, Sibu

Contract Sum : RM6,628,853.00
Date of Commencement : 02.05.2012
Date of Practical Completion : 22.08.2013
Consultant : Jurutera Perunding Wahba Sdn. Bhd.
Contractor : Polybuilding Construction Co.
Expiry Date of Defects Liability Period : 21.08.2014