                           dEVELoPMEnT                                          Progress






           26.  Contract No. SWB/CT/12/2017  The Supply, Delivery and
                Commissioning  of  Trunk  Main  Leak  Noise  Correlator  &  The
                Associated Accessories for Sibu Water Board (NRW)

                Contract Sum : RM258,693.00
                Contract Period : 14.08.2017
                Date of Practical Completion : 05.09.2017
                Contractor : Coast Enterprise (Sarawak) Sdn. Bhd.
                Expiry of Date of Warranty Period : 04.09.2018





           27.  Contract No. SWB/CT/15/2017 The Supply, Delivery, Installation
                and Commissioning of Electromagnetic Flow Meter, Pressure
                Reducing  Valve and Strainer within Sibu  Water Board Supply
                Area (NRW)
                Contract Sum : RM546,408.80
                Contract Period : 11.09.2017
                Date of Practical Completion : 10.03.2018
                Contractor : Coast Enterprise (Sarawak) Sdn. Bhd.
                Physical Work Done up to 31.1.2018 : 67.91%
                Schedule progress up to 31.1.2018 : 67.91%





           28.  Contract No. SWB/CT/16/2017 The Delivery and Laying of D.I./
                HDPE/PAC Mains,  Valves, Fittings Cum Ancillary  Works and
                Patching of Concrete Asphalt (Renewal Project Year 2017)

                Contract Sum : RM1,149,262.60
                Contract Period : 11.09.2017
                Date of Practical Completion : 10.03.2018
                Contractor : Syarikat Choo Brothers Construction
                Expiry of Date of Defects Liability Period : 20.3.2019





           29.  Work Order No. SWB/WO/13/2017 The Delivery and Laying of
                160mm O.D. HDPE Mains,  Valves and Fittings Cum Ancillary
                Works at Rumah Suhan, Jalan Sengan, Sibu

                Contract Sum : RM26,221.22
                Contract Period : 20.09.2017
                Date of Practical Completion : 19.10.2017
                Contractor : Jamaco Enterprise
                Expiry of Date of Defects Liability Period : 18.10.2018