                                Progress                                 dEVELoPMEnT







               22. Contract No. SWB/CT/06/2017  The  Supply, Delivery and
                   Commissioning of GSM/SMS/GPRS/Wireless Data Logger and
                   The Associated Accessories for Sibu Water Board (NRW)

                   Contract Sum : RM142,776.70
                   Contract Period : 02.05.2017
                   Date of Practical Completion : 12.07.2017
                   Contractor : Ahza General Work
                   Expiry of Date of Defects Liability Period : 11.07.2018



               23. Contract No. SWB/CT/07/2017 The Supply of labours, Tools and
                   Equipment for Servicing of Pressure Reducing  Valve, Strainer
                   and Altitude Valve within Sibu Water Board Supply Area (NRW)
                   Contract Sum : RM88,510.00
                   Contract Period : 02.05.2017
                   Date of Practical Completion : 01.05.2018
                   Contractor : Saraoil (M) Sdn. Bhd.
                   Physical Work Done up to 31.1.2018 : 68.37%
                   Schedule progress up to 31.1.2018 : 68.37%



               24. Contract No. SWB/CT/10/2017  The Supply of Labours for
                   Leakage  Detection,  Repair  of  Water  Mains,  Communication
                   Pipes and Pipe Appurtenances within Sibu Water Board Supply
                   Area (NRW) 
                   Contract Sum : RM1,778,468.00
                   Contract Period : 25.07.2017
                   Date of Practical Completion : 24.07.2019
                   Contractor : Syarikat Choo Brothers Construction
                   Physical Work Done up to 31.3.2018 : 41%
                   Schedule progress up to 31.3.2018 : 41%



               25. Contract  No.  SWB/CT/11/2017  The  Delivery  and  Laying  of
                   450mm M.S./400mm D.I. Mains, Valves, Fittings cum Ancillary
                   Works and Patching of Concrete Asphalt at Jalan Tunku Abdul
                   Rahman and Jalan Oya (Renewal)

                   Contract Sum : RM572,869.58
                   Contract Period : 15.06.2017
                   Date of Practical Completion : 28.09.2017
                   Contractor : Mainline Enterprise Sdn. Bhd.
                   Expiry of Date of Defects Liability Period : 27.09.2018