Page 20 - Sibu water board Final Cover
P. 20
Corporate
Progress dEVELoPMEnT
22. Contract No. SWB/CT/06/2017 The Supply, Delivery and
Commissioning of GSM/SMS/GPRS/Wireless Data Logger and
The Associated Accessories for Sibu Water Board (NRW)
Contract Sum : RM142,776.70
Contract Period : 02.05.2017
Date of Practical Completion : 12.07.2017
Contractor : Ahza General Work
Expiry of Date of Defects Liability Period : 11.07.2018
23. Contract No. SWB/CT/07/2017 The Supply of labours, Tools and
Equipment for Servicing of Pressure Reducing Valve, Strainer
and Altitude Valve within Sibu Water Board Supply Area (NRW)
Contract Sum : RM88,510.00
Contract Period : 02.05.2017
Date of Practical Completion : 01.05.2018
Contractor : Saraoil (M) Sdn. Bhd.
Physical Work Done up to 31.1.2018 : 68.37%
Schedule progress up to 31.1.2018 : 68.37%
24. Contract No. SWB/CT/10/2017 The Supply of Labours for
Leakage Detection, Repair of Water Mains, Communication
Pipes and Pipe Appurtenances within Sibu Water Board Supply
Area (NRW)
Contract Sum : RM1,778,468.00
Contract Period : 25.07.2017
Date of Practical Completion : 24.07.2019
Contractor : Syarikat Choo Brothers Construction
Physical Work Done up to 31.3.2018 : 41%
Schedule progress up to 31.3.2018 : 41%
25. Contract No. SWB/CT/11/2017 The Delivery and Laying of
450mm M.S./400mm D.I. Mains, Valves, Fittings cum Ancillary
Works and Patching of Concrete Asphalt at Jalan Tunku Abdul
Rahman and Jalan Oya (Renewal)
Contract Sum : RM572,869.58
Contract Period : 15.06.2017
Date of Practical Completion : 28.09.2017
Contractor : Mainline Enterprise Sdn. Bhd.
Expiry of Date of Defects Liability Period : 27.09.2018
15