5. Contract no. sWB/CT/27/2013 Tanjung Manis Water supply Phase 1 Package 6 – Proposed
Water Treatment and associated Facilities and high Level Tank at Tanjung Manis

Contract Sum : RM105,350,000.00
Date of Commencement : 11.11.2013
Date of Practical Completion : 24.08.2016
Contractor : Naim Engineering Sdn. Bhd.
Consultant Jurutera Perunding Wahba
Sdn. Bhd.




Remarks : Certiicate Practical Completion is to be issued. Contractor to undertake to complete overall
testing and commissioning (T&C) once the issue of raw water source is resolved.


6. Contract no. sWB/CT/28/2013 Tanjung Manis Water supply Phase 1 Package 7 – Proposed
raw Water storage reservoir and Intake and Booster Pumping station at Tanjung Manis

Contract Sum : RM71,700,000.00
Date of Commencement : 11.11.2013
Date of Practical Completion : 31.08.2016
Contractor : JV Utraco Construction Sdn.
Bhd./Pembinaan Kuantiti
Sdn. Bhd.
Consultant Jurutera Perunding
Wahba Sdn. Bhd.


Remarks : Certiicate Practical Completion had been issued. Contractor to undertake to complete
overall testing and commissioning (T&C) once the issue of raw water source is resolved.

7. Contract no. sWB/CT/29/2013 Tanjung Manis Water supply Phase 1 Package 8 – Proposed
distribution Pipelines at Tanjung Manis

Contract Sum : RM61,000,000.00
Date of Commencement : 11.11.2013
Date of Practical Completion: 31.08.2016
Contractor : Quality Concrete
Holdings Berhad
Consultant Jurutera Perunding Wahba
Sdn. Bhd.



Remarks : Certiicate Practical Completion had been issued. Contractor to undertake to complete
overall testing and commissioning (T&C) once the issue of raw water source is resolved.